In early 1985, a developer agreed to build two houses for the owner. A contractor actually built the houses and completed them by June 1, 1985. The contractor is not paid in full. No Notice of Completion was ever field. On July 1, 1986, the contractor wanted to file a Mechanic's Lien. what is true?

In early 1985, a developer agreed to build two houses for the owner. A contractor actually built the houses and completed them by June 1, 1985. The contractor is not paid in full. No Notice of Completion was ever field. On July 1, 1986, the contractor wanted to file a Mechanic's Lien. what is true?


A) He can file liens because the date of the Notice of Completion Deemed to be one year from the actual completion date
B) He can file liens because there if no time limit for filing liens
C) He can file liens because the Notice of Completion was never filed/published
D) He cannot file because the contractor can only look to the developer for payme






Learn More :